Korea 01

Manager: Private Korean Firm • Location: Yellow Sea, off the shores of South Korea
Plant: 1 x customized ZE-40-ULH LT-ORC module, nominal output 30kWE, peak output 40kWE, max η= 9%
Application: Heat recovery from engines (Heavy fuel diesel gensets)


MapThis plant - our first installation in the Far East - is located in the main hamlet of a small island located in the Yellow Sea off the southeastern shore of South Korea. This small island, occupying less than 20 km2, is home to about 3000 persons who rely for their electricity on a local power station based on eight large diesel gensets.

A Korean private firm has received from the plant owner (KEPCO) the task to increase plant efficiency. To do so it asked us to manufacture a 30-kWE nominal output Low-Temperature Organic Rankine Cycle Module with a peak output power of 40 kWE and maximum efficiency of 9% designed to operate by recovering the heat from the 1-MW diesel engine operating one of the gensets according to their specifications.

The plant - a self-contained module in open-frame, non-containerized configuration - has been located under a little awning off the main entrance to the generator room, and has been interfaced with generator #8 through a heat exchanger placed in the exhaust chimney.

The compact size of the plant has simplified shipping, while its remote interface with the Internet for control, monitoring and diagnostics has made it possible for our technicians to give real-time assistance to their colleagues performing plant start-up nearly 9000 km away.

Below you will find a photo gallery related to this plant. Click on any image to enlarge it.

Satellite view. The plant is in the SW corner of the large white buiding in the center.Satellite view. The plant is in the SW corner of the large white buiding in the center. The entrance gate to the power plant.The entrance gate to the power plant. The generators building. The ORC skid can be seen on the right, below a small awning.The generators building. The ORC skid can be seen on the right, below a small awning. The 30-kW (Max η= 9%) open-frame ORC module during installation.The 30-kW (Max η= 9%) open-frame ORC module during installation. The large diesel genset from which waste heat is recovered.The large diesel genset from which waste heat is recovered. A general view of the skid installation and the cooling tower.A general view of the skid installation and the cooling tower. The hot-side piping conveying heat to the ORC. The heat exchanger is on the platform at the top.The hot-side piping conveying heat to the ORC. The heat exchanger is on the platform at the top. A front view of the turbine.A front view of the turbine. A back view of the turbine.A back view of the turbine.